High-Rise Residential Construction - 340 on
the Park
Condo's Structural Design Could Help Cement Buyers
by Craig Barner
The downtown Chicago condominium market is among the hottest in the
nation, with abundant choices for buyers.
Gail Lissner, vice president of Chicago-based Appraisal Research
Counselors, said about 4,700 units are expected to be delivered in the
Loop in 2006, up more than 50 percent from 2005's 3,100 units. The
structural design of the $250 million 340 on the Park condominium in
Chicago's East Loop might help give the building sales advantages.
The building with curtain-wall cladding will have striking views.
Overlooking Randolph Street, 340 on the Park is immediately north of
Daley Bicentennial Plaza, northeast of the nationally famous Millennium
Park and west of Lake Shore Drive. In addition to those, the 69-story
high-rise will have vistas of Grant Park, Lake Michigan and the
landmarked Michigan Avenue streetwall.
The building had reached the 39th level in early May. Top-out is
expected in October, and the project should be finished the following
October. The concrete structure features post-tensioning, said Ola
Johansson, project manager for Seattle-based Magnusson Klemencic
Associates, the structural engineer.
A key benefit of post-tensioning is improved floor-to-ceiling height
due to thinner but equally strong slabs over a conventional structure
with "mild-steel" slabs - not a small consideration for a developer in
the Loop's superhot condominium market. The floor-to-ceiling height in
340 is 9 ft. but would have been between 8 ft., 8 in. and 8 ft., 10 in.
with a conventional system. "It's something a potential buyer would
compare with another building," Johansson added.
Moreover, the column-to-column span in 340 on the Park is 27 ft.,
Johansson said. If the building had been constructed with an 8-in.-thick
mild steel slab, the column-to-column span would have ranged between 22
and 25 ft. The wide span is mimicked in the building's first six levels
where the parking is located, though those levels have mild steel slabs.
The 10-in.-thick floor slab is strong enough to accommodate the wide
span, whereas an 8-in.-thick floor slab in the tower has sufficient
strength because of the post-tensioning.
As a result, the building's deeded 471 parking spaces are greater
than would have otherwise been the case if post-tensioning had not been
used above. "So the additional parking stalls we were able to eke out
with the post-tensioning system offset any construction premium to
install the post-tensioning," said Ron Klemencic, president of Magnusson
Klemencic.
Klemencic, who is the immediate past chairman and still a board
member of the Council on Tall Buildings and Urban Habitat, an
international association of architects and engineers headquartered in
Chicago, added that the building is possibly the world's tallest
post-tensioned concrete building and definitely Chicago's tallest such
structure. "I believe this is going to be the tallest post-tensioned
concrete building in North America," he said. "If there is a taller one,
I don't know what it is."
Tensioning a Building
The post-tensioning process involves hydraulically tensioning each
concrete floor slab. Steel tendons that are anchored to posts and
sheathed in green plastic are laid in the metal deck, and the concrete
is poured, Brandt said. After the concrete has hardened, the cables are
stressed hydraulically. More than one cable band is involved per floor,
and the number of tendons per floor ranges between 100 and 1,000.
A key issue is coordinating the layout of the cables and the lines
for the electrical, plumbing and other utility systems. Sometimes, a
conflict can arise between the two. "The post-tensioning cabling has to
go where it has to go to allow the building to act as it needs to for
structural reasons," Brandt said. "At the same time, plumbing piping has
to go where it has to go to service a bathroom or kitchen."
When a conflict arises, every party involved is assembled to find a
solution, and conflicts between post-tensioning and utility lines arise
"quite a bit," Brandt said. A cable could be swept in a new direction to
accommodate a utility line or a utility line redirected. Typically, the
post-tensioning cable gets priority over utility lines "to allow the
building to stand up at the end of the day," Brandt said. In some cases,
however, the post-tensioning cables are moved and extra reinforcing
steel is added in that area for stiffness. Cost-effectiveness and
owner's requirements are considered in making the decision.
Buildings have been post-tensioned in Midwest before, but Klemencic
said the process is more common on the West Coast and Southeast partly
because of building tradition. As a result, crews on the 340 project
were a little apprehensive about the process because they wanted to
maintain a three-day pour cycle per floor. "In the beginning, they were
talking about maybe four or even five days per floor, but they've been
executing it three days per floor," Klemencic said. That means the
project is ahead of schedule.
An Unused Site
The project is on a previously unused lot between the Blue Cross
Blue Shield office on the west and The Buckingham condominium on the
east. Only a half-story is below grade in landfilled area, and the first
six levels will hold the parking and face Lower Lower and Lower Randolph
Street. The first condominium level is two floors above Upper Randolph
Street - or the eighth level overall.
The 975,000-sq.-ft. building will hold 344 condominium units that
range between about 1,000 and 5,000 sq. ft. in one-, two- and
three-bedroom layouts, said Don Biernacki, senior vice president of
Chicago-based LR Development Co., the developer. Customizable penthouse
units start on level 57. Neither the percentage of units sold nor unit
costs was released.
About 4,000 sq. ft. of space on the seventh floor, which is flush
with Upper Randolph Street, will hold retail. The building will feature
an amenity floor on the 25th level, including a pool and fitness
facility. A "signature" building was sought, so a quality aesthetic
design and finishes were needed, Biernacki said. Rather than just only
curtain wall, the exterior features variation with protruding and inset
balconies and horizontal and vertical lines. Inside, bamboo - a
sustainable material - is used for the typical unit flooring, and there
will be high-end cabinets, faucets and other items.
Locating Lower, Lower Randolph
The maze of streets beneath Chicago's normal level can be confusing
for those drives not used to navigating the city's lower depths. An
issue on the $250 million 340 on the Park condominium project was the
access point on Lower Lower Randolph Street.
Materials are coming from points all over the country, and "the lower
roads are difficult to explain to someone on how to get there," said
Bert Brandt, senior project in Chicago with Bovis Lend Lease Inc., the
general contractor. MapQuest, the popular Internet site often used for
navigation, would prove useless if trying to map a route to the lower
depths of Randolph because it does not include the below normal grade
streets.
"More than a couple times" a delivery was expected but went missing,
and someone was dispatched to find the driver on the streets of downtown
Chicago, Brandt said. Other times, deliveries meant for other projects,
such as those in the nearby Lakeshore East development, came into 340's
lot, he added.
As a result, drivers are instructed to call the field office before
making a delivery, and specific directions are given. But the site below
the city's normal grade proved an advantage when it came to constructing
formwork. The large amount of space on grade has allowed large flying
forms, rather than stick-built forms, to be used on the project. A
spillover benefit is that flying forms allow the teams to maintain their
three-day pour cycle. "In Chicago, you don't see flying forms often
because you're in boxed-in sites," Brandt added.
Other issues arose on the project:
Numerous obstructions were encountered on the project, including a
"forest of wood pilings" probably used as retaining walls decades ago
when Lake Michigan's shoreline was west of its present location, Brandt
said. Old boat docks and haul roads were also discovered.
Backhoes were used to demolish most obstructions. But some
impediments, such as old retaining walls, were extracted with a chain.
Because of the project's closeness to the lake, groundwater infiltrated
the site. Water wells were drilled and pumped. About 75 percent of
construction waste has been sorted because a goal to achieve Leadership
in Energy and Environmental Design certification. Also as part of
certification, a percentage of materials has been obtained from within
500 mi. of the site.
 |